Postnatal & Administration Washroom Renewal
Modern Government Maternity Hospital (MGMH) · Hyderabad, Telangana
Executive Summary
Administration, family planning ward and postnatal washrooms required comprehensive renewal.
Impact Highlights
15 units
Washroom units documented
Before-and-after units documented in the VS-008 project profile
Scope of Work
Postnatal ward, family planning ward and administrative wing.
Major Works Executed
Drainage rehabilitation, plumbing replacement, waterproofing, flooring and fixtures.
Before & After Transformation
BEFORE
AFTERLining 2 (I-18)
We have installed the fixtures like jaali and tap
BEFORE
AFTERNurse changing room 2nd floor
We have installed the fixtures like Pillar cock, Angle cock and connection pipe
BEFORE
AFTERLYC (III-31)
We have installed the fixtures like jaali and tap
BEFORE
AFTERLYC (III-32)
We have installed the fixtures like jaali and tap
BEFORE
AFTERLYC (III-33)
We have installed the fixtures like jaali and tap
BEFORE
AFTERStore room
We have installed waste pipe, jaali and we did grouting for flooring
BEFORE
AFTERAO Room (III-34)
We have instllaed the door
BEFORE
AFTERFamily planning ward right lobby
We have installed the washbasin taps, waste pipes, connection ppes and jaali
BEFORE
AFTERFamily planning ward left (III-19)
We have installed the fixtures like jaali and tap
BEFORE
AFTERFamily planning ward left (III-13)
We have installed the fixtures like jaali, Flush tank, seat cover and tap
BEFORE
AFTERFamily planning ward left (III-12)
We have installed the fixtures like jaali, Flush tank, seat cover and tap
BEFORE
AFTERFamily planning ward left (III-11)
We have installed the fixtures like jaali, Flush tank, seat cover and tap
BEFORE
AFTERFamily planning ward left (III-20)
We have installed the fixtures like jaali and tap
BEFORE
AFTERPNW right III-10
We dismantled the bathroom and laid new tiles and installed the fixtures like tap and jaali
BEFORE
AFTERPNW right (III-9)
We dismantled the bathroom and laid new tiles and installed the fixtures like tap and jaali
Project Budget
| Component | Amount | |
|---|---|---|
| Blockage Rehabilitation | ₹3,60,000 | |
| Repair Works | ₹1,12,775 | |
| Total Project Budget | ₹4,72,775 | |
Expected Impact
Safer and more dignified facilities for patients and staff.
Partners
Vikasa Tarangini (India), VT Seva (USA), MGMH Hospital Administration
Help Us Transform the Next Hospital
Your support funds documented, transparent projects like this one — with every rupee accounted for.